Date | Activity |
---|---|
October 2024 | Octavius were announced as the project contractor. Design stage began. |
February 2025 | Site investigations and surveys |
February to May 2025 | Site set up and start of preparatory works |
Summer 2025 | Building of temporary pedestrian bridge and utility diversions |
Autumn 2025 | Temporary pedestrian bridge complete. Utility diversion works. |
End of 2025 | Winterstoke Road Bridge closed to motor vehicles. Demolition of main bridge. |
Early until mid 2026 | Foundation works |
Mid to end of 2026 | Construction of the new bridge |
Early 2027 | Utility diversions back to main bridge. Landscaping works. |
Spring 2027 | Construction of the road. Winterstoke Road reopens to all traffic. |
Spring to Summer 2027 | Demolition of temporary bridge |
Summer 2027 | Works complete |